Project 17-A, stealth frigate programme: Navy insists on building two frigates abroad

by Ajai Shukla
Business Standard
Mazagon Dock Ltd, Mumbai, March 27, 2009

The Indian Navy’s Project 17 is nearing completion; three Indian-designed-and-built stealth frigates of the Shivalik class are on track to enter service. Now, attention has switched to Project 17-A, the country’s biggest-ever naval purchase, a Rs 17,000 crore plan to build seven stealth frigates that are even more advanced than the Shivalik class.

The Cabinet Committee on Security (CCS) has long cleared the project, but no order has yet been placed by the Ministry of Defence. Business Standard has learned that the order is held up by a difference of opinion between the shipyards and the navy on where these frigates should be built.

The two defence shipyards capable of manufacturing 5000-tonne frigates — Mazagon Dock Limited, Mumbai (MDL) and Garden Reach Shipbuilders and Engineers, Kolkata (GRSE) — argue that Project 17-A should be built entirely in India. The Indian Navy insists that the first two frigates should be built in a foreign shipyard. After the Indian shipyards have observed how it is done, they can build the next five vessels.

At the heart of the disagreement is a new, highly advanced building method — modular shipbuilding — that India will use for Project 17-A, and for all projects thereafter.

Conventional shipbuilding was relatively simple: first weld together a steel hull, and then put in the engines, piping, electrical wiring, fitments, weaponry and electronics that make it a fighting platform. Modular shipbuilding is far more complex, akin to a giant Lego game. The warship is built in 300-tonne blocks, each block complete with all the piping, electrical wiring and fitments that form a part of the ship. Then these 300-tonne blocks are brought together by giant cranes and assembled into a complete warship.

This creates an entirely different set of design challenges. Each bulkhead wall, each pipe, each cable, and each electronic component in a 300-tonne block must precisely connect with its counterpart in the neighbouring block. Each block is designed separately, but all of them must come together in perfect alignment.

This method has never been used by either MDL or GRSE; they accept the need for a foreign design partner. But both shipyards, having successfully built frigates of the Brahmaputra and the Shivalik class, claim they already have the expertise needed to build Project 17-A, based on the foreign partner’s drawings. Admiral HS Malhi, Chairman and Managing Director (CMD) of MDL says, “We need to go abroad for the production drawings… But for actual modular construction, no technology is required to be transferred”

The Navy believes that if MDL and GRSE try to master this skill while they build the first Project 17-A frigates, the entire programme will be delayed unacceptably. Instead, the Director of Naval Design, Rear Admiral MK Badhwar, says the foreign design partner selected should built the first two frigates in his own shipyard, observed by Indian workmen who can thereby pick up the skills.

The DND says, “This will also make the vendor demonstrate “buildability”. He must demonstrate that his design can be actually built into a warship, using modular construction, in four years. That will create a demonstrated benchmark for GRSE and MDL; otherwise, if there are delays later, our shipyards could argue that the foreign yard too would have taken a long period to build each frigate.”

The MoD’s is finding it difficult to reconcile these two viewpoints, partly because a decision to build two frigates abroad would sharply escalate the cost of Project 17-A. Each Shivalik class stealth frigate, built in MDL, cost Rs 2000-2500 crores. The bill for a comparable frigate, built in a European shipyard for the Australian navy, has come to more than double that figure.

9 comments:

  1. I think paying a billion dollars to learn modular shipbuilding from the masters is worth it... however, we need to ensure that we do learn how it is done - ToT, plans, training, the whole hog. That is the only way we'll get our money's worth.

    I think its a good thing to see our local shipyards looking so confident

    ReplyDelete
  2. Thanks Ajai Ji for this post and update on Project 17A.
    Recenly there was a news of another batch of 4 Shivalik class will be built by MDL or GRSL after commissioning of the current Shivalik class.
    I am assuming that is separate of 7Project 17 A class FFGs to be built after the current shivalik class.

    http://www.bharat-rakshak.com/NEWS/newsrf.php?newsid=10694

    says......
    ...................
    On the Navy's other future project, the sources said the building of four new guided missile stealth frigates, as a follow-on of the Shivalik class being built at MDL, has been approved and their construction would also be launched soon, taking the number in this class of warships to seven.
    .....................

    Couuld you please clarify ?

    Regards,

    ReplyDelete
  3. Ajai, is there any possibility that Project 17A may go to some private sector shipyard or will the government shipyards retain monopoly over naval projects.

    ReplyDelete
  4. Isn't the IAC built using the the same modular technology ?

    ReplyDelete
  5. In order to undertake such modern projects I wonder if the shipyards have been updated with modern technology and working environment.If one compares western indutrial complexes with Indian ones I think this is a worry.A modernized work area, capability and workforce would need to be in place before undertaking such project, so I think instead of one of those promises that never gets kept,it is better to build a couple overseas, learn and duplicate the effort which would be goog for the country and better in the long run.

    ReplyDelete
  6. The report about 4 additional Shivalik class frigates is incorrect.

    No question about private sector shipyards constructing warships as yet. They simply don't have the technology or experience base in place yet.

    There is an 800 crore rupee infrastructure update programme going on in MDL... and GRSE is updating as well.

    ReplyDelete
  7. The biggest problem that our shipyards face today - And you can see the yards on google earth : Mazgaon docks, Chochin Shipyard, Goa Shipyard, Garden Reach Shipyard is space.

    There is just no space in either of these to build simultaneously several ships at one go. Add to this the older method of building by first laying the keel and then building upwards, and the special unionized rate of ship building means that a 5000 ton frigate will take upwards of 6 - 7 years before it is handed over to the Navy.

    At least the space requirement part and the speed part can be solved by simultaneously building blocks elsewhere (Even inland) - and with private participation and be transported to the shipyard to be finally assembled within a short time and put into the water.

    ReplyDelete
  8. Thanks again Ajai Ji,for clarifying my question ..I think DNA is doing lots misinformation campaign on purpose...The point to note that they are doing just before the election..only thing is unknown..on whose behest ?

    Regards,

    ReplyDelete
  9. i thought indian shipyard mazagaon docks are already constructing the iac by the modular method. please explain where the problem is. thanks.

    ReplyDelete

Recent Posts

<
Page 1 of 10412345...104Next >>Last